Question: 1.The estimate upon completion (EAC) for the project is $ 140,000. The cost performance index (CPI) is .80. What is the project budget at the

1.The estimate upon completion (EAC) for the project is $ 140,000. The cost performance index (CPI) is .80. What is the project budget at the end (BAC) a) 220,000 b) 140,000 c) 112,000 d) 175,000

2.The project consists of rebuilding a historic bridge as part of a long-term community restoration project. The budget is 500,000. Time is moving fast. WE ARE AT THE END OF THE NINTH MONTH OF A 12 MONTH PROJECT. 90% of the work is completely finished. $ 360,000 has been spent for the work that is completed. The Cost Performance Index (CPI) is: a) 1.20 B) 0.90 c) 1.25 d) .80