Question: 1.When gathering the information needed for the program predictability measure, the Release Train Engineer (RTE) meets resistance from teams that the business value does not
1.When gathering the information needed for the program predictability measure, the Release Train Engineer (RTE) meets resistance from teams that the business value does not reflect the real effort and progress made during the Program Increment (PI).
What are two considerations the RTE should make when coaching the team to give them a better feeling on what they have actually created? (Choose two.)
x-Work with the team to ensure they are actively involved when the Business Owners score the business value achieved
x-Coach the Business Owner's review of objectives to see that scoring is against the specific details negotiated with the team during PI Planning
-Illustrate the linkage between business values and the market communications/release objectives tied to the three to six month Enterprise strategy
-Educate teams that business value provides the Enterprise with a Metric of how fast the team executed work during the PI
-Publish the team business values and coach teams that these values are for tracking each Agile Release Train deliverable