1-Which of the following is true of projects? a-They are permanent in nature. b- They have an...
Question:
1-Which of the following is true of projects?
a-They are permanent in nature.
b- They have an indefinite beginning and end.
c- They are developed using regressive elaboration.
d- They have a unique purpose.
2-Which of the following is NOT one of the ProjectManagement Process Groups used by both traditional (waterfall) andAgile (adaptive) methodologies.
a- Planning
b- Execution
c- Design
d- Closing
3- What is a key question you will ask and answer as aproject manager?
a- What is our plan?
b- How will we solve it?
c- All of these
d- What problem are we solving?
4- The three main components of a project are
a- Product (scope), Schedule, and Resources (budget)
b- The team, the stakeholders and the users
c- Products, Processes and Priorities
d- Software, hardware and networkss.
5- The Monitoring and Controlling process groupincludes
a- Assigning people to tasks needed to create deliverables
b- Developing a detailed schedule
c- Comparing performance to plans
d- Doing the tasks needed to create the deliverables
6- Initiating processes may include
a- All of these
b- Defining high-level expectations
c- Determining expected resource budgets
d- Identifying an initial list of stakeholders that may play arole in the project
Advanced Accounting
ISBN: 978-0077431808
10th edition
Authors: Joe Hoyle, Thomas Schaefer, Timothy Doupnik