Question: [ 2 0 points ] Using the forward pass / backward pass C P M 5 technique and the AOA / ADM activity network diagram

[20 points]
Using the forward pass/backward pass CPM5 technique and the AOA/ADM activity network diagram (for
the project) below:
i. Determine the activities on the project's critical path (5 points)
ii. Determine the project duration (5 points)
iii. Reverse engineer the activity schedule (Activity IDs, Durations, and Precedence Relationships)
(10 points)
The numbers on the arrows/arcs/links represent the activity durations (in days). A pair of connected nodes
(e.g.1-2, or 4-6) represents an activity or dummy activity.
 [20 points] Using the forward pass/backward pass CPM5 technique and the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!