Question: [ 2 0 points ] Using the forward pass / backward pass C P M 5 technique and the AOA / ADM activity network diagram
points
Using the forward passbackward pass technique and the AOAADM activity network diagram for
the project below:
i Determine the activities on the project's critical path points
ii Determine the project duration points
iii. Reverse engineer the activity schedule Activity IDs, Durations, and Precedence Relationships
points
The numbers on the arrowsarcslinks represent the activity durations in days A pair of connected nodes
eg or represents an activity or dummy activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
