Question: Scheduling Exercise 6 Critical Path Method ( CPM ) Activity on the Arrow ( AOA ) Forward Pass, Backward Pass, Total Float For each project,

Scheduling Exercise 6
Critical Path Method (CPM)
Activity on the Arrow (AOA)
Forward Pass, Backward Pass, Total Float
For each project, verify if the diagram is correct; add or remove requisite links (arrows,
dummies). Do a forward pass to calculate the early start and the early finish of each activity.
Do a backward pass to calculate the late start and the late finish of each activity. Determine the
total float of each activity. Highlight the critical path on the CPM diagram and answer the
following questions (1 point each):
Part 1(4 Points)
1. How long does the project take? ______ days
2. What is the early start of activity N? day ______
3. What is the late finish of activity O? day ______
4. Which activity lists a redundant predecessor ______
Part 2(6 Points)
5. How long does the project take? ______ days
6. What is the late start of activity R? day ______
7. What is the early finish of activity L? day ______
8. If activity D is delayed by 3 days,
what is the length of the overall project? ______ days
9. If activity T is delayed by 10 days,
what is the length of the overall project? ______ days
10. What activities are on the critical path? ___________
-

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!