Question: 2 [ 1 4 ] A consulting engineer has been hired to advise a town on how best to proceed with the construction of a
A consulting engineer has been hired to advise a town on how best to proceed with the construction of a water supply reservoir. Since only of storage will be required for the next years, an alternative to building the full capacity now is to build the reservoir in two stages. Initially, the reservoir could be built with of capacity and then, years later, the additional of capacity could be added by increasing the height of the reservoir. If interest is computed at which construction plan is preferred?
Annual
tableConstruction Cost,Maintenance CostBuild in two stages:,,First stage: reservoir,$$