Question: 2 . 1 8 Given the following project ( all times in days ) Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A

2.18 Given the following project (all times in days)
Activity
Predecessor
Normal Time
Normal Cost
Crash Time
Crash Cost
A
-
3
$40
2
$80
B
A
2
$20
1
$80
C
A
2
$20
2
$20
D
A
4
$30
1
$120
E
B
3
$10
1
$80

Step by Step Solution