Question: 2 . 1 Read carefully and answer the questions. For the Mega IT company project, you have to keep control over the cost of the
Read carefully and answer the questions.
For the Mega IT company project, you have to keep control over the cost of the project. Phase
will take six months to complete, and you are three months into it The control units
represent working hours.
The partial structure of Phase is as follows:
For A and which are subyacgonts of the Phase account, you have the following information:
Calculate the following values:
Cost variance CV
A
B
Schedule variance SV
A
B
Schedule performance index SPI
AI
BI