Question: 2 . 1 Read carefully and answer the questions. ( 1 2 ) For the Mega IT company project, you have to keep control over
Read carefully and answer the questions.
For the Mega IT company project, you have to keep control over the cost of the project. Phase will take six months to complete, and you are three months into it The control units represent working hours.
The partial structure of Phase is as follonic.
For A and which are subaccounts of the Phase account, you have the following information:
baselined vost. sche duled
OF
tabletableProjectSubAccountBCAC,ACWP,BQAC,AQWP,tablePercentagecompleteBCWSAB
Calculate the following values:
Cost variance
A
B
Schedule variance SV
A
B
Schedule performance index SPI
I
AI
BI