Question: 2. (12 points) Based on the project network given below, develop a resource schedule in the loading chan that follows using the parallel method and
2. (12 points) Based on the project network given below, develop a resource schedule in the loading chan that follows using the parallel method and heuristics (minimum slack; smallest duration; lowest identification number). Note: Activities 1,3,5, and 6 use fwo of the resource skills. Three of the resource skills are available. What is the onder in which your activities are scheduled? What are the sehedule slacks for activities 1 , 3, and 4 ? \begin{tabular}{|l|l|l|} \hline 0 & 1 & 4 \\ \hline 3 & 2 & 3 \\ \hline 3 & 4 & 7 \\ \hline \end{tabular} The order in which your activities are scheduled: Slack for activities: Activity 1 : Activity 3 : Activity 4