Question: 2. Based on the project network given below, develop a resource schedule in the loading chart that follows using the parallel method and heuristics (minimum
2. Based on the project network given below, develop a resource schedule in the loading chart that follows using the parallel method and heuristics (minimum slack; smallest duration; lowest identification number). Note: Activities 1, 3, 5, and 6 use two of the resource skills. Three of the resource skills are available. What is the order in which your activities are scheduled? What are the schedule slacks for activities 1, 3, and 4?