Question: 2 2 2 3 2 4 2 4 table [ [ Activity , table [ [ Preceding ] , [ activity ] ]

22232424
\table[[Activity,\table[[Preceding],[activity]],Optimistic,Pessimistic,Most likely],[A,,1,7,5],[B,A,4,8,6],[C,A,5,7,6],[D,B,1,5,3],[E,C,2,5,4],[F,D, E,2,6,4],[G,C,4,8,5],[H,F, G,3,5,4]]
What is the earliest time to finish the project?
18.7
20
21.7
22.5
26.2
 22232424 \table[[Activity,\table[[Preceding],[activity]],Optimistic,Pessimistic,Most likely],[A,,1,7,5],[B,A,4,8,6],[C,A,5,7,6],[D,B,1,5,3],[E,C,2,5,4],[F,D, E,2,6,4],[G,C,4,8,5],[H,F, G,3,5,4]] What is the earliest time to