Question: tual code de a Activity Predecessor Normal time A 2 B 3 C B A 5 G. F H 15 HH 2 D N M,

tual code de a Activity Predecessor Normal time A
tual code de a Activity Predecessor Normal time A
tual code de a Activity Predecessor Normal time A 2 B 3 C B A 5 G. F H 15 HH 2 D N M, J 1 - Construct Work Breakdown Structure (WBS) refer to course lectures - Construct Linear Responsibility Chart (LRC) -refer to course lectures - Assume at least 15 reasonable activities in the project - Construct precedence table (Activities, Predecessors, and Duration table) - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network (AON) - Calculate slack of each activity - Determine the critical paths. There must be at least 2 critical paths 3. Perform a PERT Analysis assuming reasonable optimistic, most likely and pessimistic times for each activity from milestone 1. 4. Perform a crashing analysis assuming reasonable crashing costs and normal costs for each activity from milestone 1. tual code de a Activity Predecessor Normal time A 2 B 3 C B A 5 G. F H 15 HH 2 D N M, J 1 - Construct Work Breakdown Structure (WBS) refer to course lectures - Construct Linear Responsibility Chart (LRC) -refer to course lectures - Assume at least 15 reasonable activities in the project - Construct precedence table (Activities, Predecessors, and Duration table) - Calculate early start (ES), early finish (EF), late start (LS) and late finish (LF) for each activity - Draw Activity on Arrow network (AOA) - Draw Activity on Node network (AON) - Calculate slack of each activity - Determine the critical paths. There must be at least 2 critical paths 3. Perform a PERT Analysis assuming reasonable optimistic, most likely and pessimistic times for each activity from milestone 1. 4. Perform a crashing analysis assuming reasonable crashing costs and normal costs for each activity from milestone 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!