Question: 2 2 5 1 4 Question 1 , Problem 6 . 2 . 1 4 Part 2 of 2 A business organisation is trying to
Question Problem
Part of
A business organisation is trying to improve staff morale and motivation and has decided to replace the detailed list of the various activities that will need to be completed, together with an estimate of how long following table.
tableActivityDuration,tablePrecedingactivitiestablePersonnelrequiredAPurchase construction materials, weeks,BtablePurchase catering equipmentneeded for new cafeteria weeks,CAppoint supervisory architect, weeks,DClear site, weeks,Produce final building details, weeks,C DFPrepare site for construction, weeks,GConstruct cafeteria, weeks,Install utility services, weeks,GInstall catering equipment, weeks,JDecorate internally, weeks,Stock cafeteria, weeks,I,Hire catering staff, weeks,Train staff on site, weeks,I,
a Identify the critical path.
b Determine float times for all activities.
a The critical path is CEFGHIM
b
tableActivityDuration,FloatABC
Find a and b
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock