Question: 2 2 5 1 4 Question 1 , Problem 6 . 2 . 1 4 Part 2 of 2 A business organisation is trying to

2251
4
Question 1, Problem 6.2.14
Part 2 of 2
A business organisation is trying to improve staff morale and motivation and has decided to replace the e detailed list of the various activities that will need to be completed, together with an estimate of how long following table.
\table[[Activity,,Duration,\table[[Preceding],[activities]],\table[[Personnel],[required]]],[A,Purchase construction materials,11 weeks,-,3],[B,\table[[Purchase catering equipment],[needed for new cafeteria]],2 weeks,-,2],[C,Appoint supervisory architect,3 weeks,-,1],[D,Clear site,2 weeks,-,3],[E,Produce final building details,8 weeks,C, D,1],[F,Prepare site for construction,2 weeks,E,2],[G,Construct cafeteria,12 weeks,A,F,5],[H,Install utility services,4 weeks,G,2],[1,Install catering equipment,3 weeks,B,H,2],[J,Decorate internally,2 weeks,B,H,2],[K,Stock cafeteria,2 weeks,I,J,1],[L,Hire catering staff,9 weeks,-,2],[M?,Train staff on site,3 weeks,I,L,3]]
(a) Identify the critical path.
(b) Determine float times for all activities.
(a) The critical path is C-E-F-G-H-I-M .
(b)
\table[[Activity,Duration,Float],[A,11,],[B,2,],[C,3,
Find (a) and (b)
 2251 4 Question 1, Problem 6.2.14 Part 2 of 2 A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!