Question: 2 2 . A company using DBR has an order with a shipping buffer of 1 0 days is due on 6 / 2 0

22. A company using DBR has an order with a shipping buffer of 10 days is due on 6/20. Today is 6/15. The company works 7 days a week. The buffer consumption is now:
a.20%
b.0%
c.100%
d.50%
To the right is a traditional project network showing project dependencies and current task estimates using traditional approaches in days. There is only one of each resource (A, B, C, D, E, and F). Using the CCPM approach to project management, please answer the next 3 questions.
23. The critical chain consists of:
a. B -B -B -D -F
b. A-C-B-D-F
c. A-C-B -D -F
d. B-A-B-B-C-F