Question: 2 2 . Consider a single machine scheduling problem with 5 jobs ( / 1 to J 5 ) . The minimum mean flow time
Consider a single machine scheduling problem with jobs to J The
minimum mean flow time for this problem is days. Let the job sequence
corresponding to this minimum mean flow time be denoted by S
For simplicity, let S UJJJJ When the jobs are arranged in this
sequence, the respective job processing times follow an arithmetic
progression.
If the difference between the processing times of the last job and the first
job in this sequence is days, find the processing times of all the five
jobs.
marks