Question: 2 . 2 . TCPI Scenario [ 2 points ] Consider the below project data: BAC = $ 5 7 5 , 0 0 0

2.2. TCPI Scenario [2 points]
Consider the below project data:
BAC = $575,000
EV = $230,000
AC = $252,000
The project is approximately 40% complete (i.e. EV/BAC).
1. What TCPI is required to bring this project in on the current budget (BAC)?
2. Considering the past cost performance index, what should be the performance improvement to bring the project at the current BAC?