Question: SCENARIO 2 ( 2 5 Points ) You have a project to build a new fence. The fence will form a square. Each side is

SCENARIO 2(25 Points)
You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. But. circumstances changed on the project, and work on the sides was able to proceed in parallel, so more than one side can be worked on at the same time. Today is the end of day 3. Using the following project status chart, answer the questions below the chart.
Activity Day1
Day 2
Day 3
Side 1S..........F
spent $1,000
Side 2
S.PF-F
Side 3 PS-S-PF
$600
Side 4
S-----
600
Day 4
PS PF
Status End of Day 3
Complete,
50% done, spent
75% done, spent
S= Actual Start, F= Actual Finish, PS= Planned Start, and PF= Planned Finish
Questions:
Calculate: PV
EV
AC
BAC
CV
CPI
Calculate: SV
SPI
EAC
ETC
VAC
 SCENARIO 2(25 Points) You have a project to build a new

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!