Question: 2 3 4 5 6 7 8 9 P301 Project Mgt. Problem Task Optimistic Most Likely Pessimistic 2 12 B 8 14 26 6 15


2 3 4 5 6 7 8 9 P301 Project Mgt. Problem Task Optimistic Most Likely Pessimistic 2 12 B 8 14 26 6 15 18 D 8 11 20 E 6 14 22 F 7 9 17 S 7 15 H 7 8 9 3 9 21 S 7 15 K 10 19 40 1 8 20 M 2 3 10 11 12 13 J 14 15 1 16 D 12 7 1 10 18 17 18 19 20 21 22 23 24 25 26 27 28 Start B 15 E 14 M 2 K 20 14 Sheet1 A 7 8 9 D 12 8 -- 10 M 2 00 1 22 18 B 23 Start 15 E 24 14 K 25 20 26 27 28 29 14 F H L 30 10 >> 8 12 31 32 1. What is the critical path for this project? 33 34 2. What is the slack on each activity? 35 36 3. What is the probability of completing the critical path in 60 weeks? 37 38 4. What completion time would give you a 99% confidence of completing the critical path on-time? 39 40 41