Question: 2 & 3 please!! QUESTION 2 If the net present value (NPV) of a capital budgeting project is greater than zero, then: O A. the
QUESTION 2 If the net present value (NPV) of a capital budgeting project is greater than zero, then: O A. the project's value is less than its price. O B. the project's value is greater than its price. OC. the project should be accepted. O D. both A and C. O E. both B and C. QUESTION 3 For a capital budgeting project with a positive net present value (NPV): O A. the project's internal rate of return (IRR) is less than the WACC. O B. the project's internal rate of return (IRR) is greater than the WACC. O C. the project's internal rats of return (IRR) is equal to the WACC. O D. the project's internal rate of return (IRR) is equal to zero. O E. none of the above is true
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
