Question: 2 5 . 6 . The relationship between people and time is highly nonlinear. Using Putnam s software equation ( described in Section 2 5

25.6. The relationship between people and time is highly nonlinear. Using Putnams software
equation (described in Section 25.8.2), develop a table that relates number of people to project
duration for a software project requiring 50000 LOC and 15 person-years of effort (the
productivity parameter is 5000 and B =0.37). Assume that the software must be delivered in
24 months plus or minus 12 months.