Question: 2 . 5 Estimated activity times and precedences are given below: table [ [ , Times ( days ) , Required ] , [

2.5 Estimated activity times and precedences are given below:
\table[[,Times (days),Required],[Activity,Optimistic,Most likely,Pessimistic,\table[[Recedence],[preceder]]],[A,6,7,14,-],[B,8,10,12,-],[C,2,3,4,-],[D,6,7,8,A],[E,5,5.5,9,B, C],[F,5,7,9,B, C],[G,4,6,8,D, E],[H,2.7,3,3.5,F]] Using the traditional statistical approach, what is the probability that the project will be completed within.
 2.5 Estimated activity times and precedences are given below: \table[[,Times (days),Required],[Activity,Optimistic,Most