Question: [ 2 5 pts . ] The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5 ,

[25 pts.] The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5,B=3,C=11,D=4,E=7,F=6,G=4,H=3,I=5,J=6 and K=4.
a. Apply Critical Path Method and calculate the ES, EF, LS, LF, and Slack for each activity. (Draw table)
b. What is the critical path of this network?
c. What is project completion time?