Question: [ 2 5 pts . ] The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5 ,
pts The network below represents a project being analyzed by Critical Path Methods. Activity durations are and
a Apply Critical Path Method and calculate the ES EF LS LF and Slack for each activity. Draw table
b What is the critical path of this network?
c What is project completion time?