Question: The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and

The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.

a. What task must be on the critical path, regardless of activity durations?

b. What is the duration of path A-B-E-H-J?

c. What is the critical path of this network?

d. What is the length of the critical path?

e. What is slack time at activity H?

f. What is the Late Finish of activity H?

g. If activity C were delayed by two time units, what would happen to the project duration?

The following table provides the information necessary to construct a project network and project crash data.

Activity Time (weeks)

Activity Cost ($)

Activity

Activity Predecessor

Normal

Crash

Normal

Crash

A

--

16

8

2000

4400

B

--

14

9

1000

1800

C

A

8

6

500

700

D

A

5

4

600

1300

E

B

4

2

1500

3000

F

B

6

4

800

1600

G

C

10

7

3000

4500

H

D, E

15

10

5000

8000

Construct the project network, and crash the network the maximum amount possible.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!