Question: 2. (50 pts.) A project has been defined to contain the following activities, along with their time estimates (in weeks) for completion: Optimistic Most likely

2. (50 pts.) A project has been defined to contain the following activities, along with their time estimates (in weeks) for completion: Optimistic Most likely Pessimistic Immediate Activity time time time Predecessor A 1 4 7 B 2 6 7 A C 3 4 6 D D 6 12 14 A E W 6 12 D 6 8 16 B, C G 5 6 E, F