Question: Question 2. 50 points A project has been defined to contain the following activities, along with their time estimates (in weeks) for completion: Activity Optimistic

Question 2. 50 points A project has been defined
Question 2. 50 points A project has been defined to contain the following activities, along with their time estimates (in weeks) for completion: Activity Optimistic time 1 Immediate Predecessor Most likely time 4 6 A 2 3 4 Pessimistic time 7 7 6 14 12 16 6 D 6 E 3 6 12 6 8 5 D B,C E, F G 1 What is the probability that this project will take over (e., more than) 32 weeks to complete