Question: 2. A company is considering two possible projects and uses an 8% MARR. Show all work a. Which project should be selected if future worth

2. A company is considering two possible projects and uses an 8% MARR. Show all work a. Which project should be selected if future worth analysis is used? (15 points) b. Which project should be selected if payback period is used? (15 points) Investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A $85,000 $25,000 $25,000 $25,000 $25,000 $25,000 Project B $110,000 $25,000 $30,000 $35,000 $40,000 $45,000