Question: 2- A project consists the activities shown bellow, all links are Finish to Start ( F-S) with Zero duration Activity Duration (weeks) Predecessor A 4

2- A project consists the activities shown

2- A project consists the activities shown bellow, all links are Finish to Start ( F-S) with Zero duration Activity Duration (weeks) Predecessor A 4 B 3 C 6 A,B D 1 B E 7 D F 2 5 C, E H 8 E J 4 G K 5 F,G L 6 J,H M 3 L,K a) Draw the activity network ( logic diagram ) b) Draw Gantt chart ( bar chart) c) Determine the total time of the project? d) Identify the critical path? e) What is the value of float in activities A,D,E,F,K and H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!