Question: 1- For the given 6-M maintenance plan, the following activities will be done, links with Finish to Start (F-S) with Zero duration Activity Predecessor

1- For the given 6-M maintenance plan, the following activities will be 

1- For the given 6-M maintenance plan, the following activities will be done, links with Finish to Start (F-S) with Zero duration Activity Predecessor Duration (Day) A B C E --- A A A C&D 8 5 6 8 20 1. Construct the project network (logic diagram)? 2. Identify the critical activities? 4. Construct the corresponding Gantt chart? completion time 3. Identify the critical path? 5. Calculate the project