Question: 2. A project has seven activities. NormalNormalCrashCrashMaximum ImmediateTimeCostTimeCostWeeks Activity Predecessors (weeks) ($) (weeks) ($) Reduced Anone43,00035,0001 BA95,00078,0002 CA47,00047,0000 DB, C66,00048,0002 EC84,00068,0002 FD34,00029,0001 GE, F42,00027,0002 (a)
2. A project has seven activities.
NormalNormalCrashCrashMaximum
ImmediateTimeCostTimeCostWeeks
ActivityPredecessors(weeks)($) (weeks)($) Reduced
Anone43,00035,0001
BA95,00078,0002
CA47,00047,0000
DB, C66,00048,0002
EC84,00068,0002
FD34,00029,0001
GE, F42,00027,0002
(a) What is the expected project completion time?
(b) What is the critical path?
(c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks?