Question: 2. A project has seven activities. Maximum Weeks Reduced Normal Immediate Time Activity Predecessors (weeks) A none 4 B A 9 A 4 D B,

2. A project has seven activities. Maximum Weeks
2. A project has seven activities. Maximum Weeks Reduced Normal Immediate Time Activity Predecessors (weeks) A none 4 B A 9 A 4 D B, C 6 E F D 3 G E, F 4 Normal Cost ($) 3,000 5,000 7,000 6,000 4,000 4,000 2,000 Crash Time (weeks) 3 7 4 4 6 2 2 Crash Cost () 5,000 8,000 7,000 8,000 8,000 9,000 7,000 2 0 2 2 1 2 (a) What is the expected project completion time? (b) What is the critical path? (c) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks