Question: 2. A small software development project at Krishna Dhar's firm has five major activities. The times (in days) are estimated and provided in the table

2. A small software development project at Krishna Dhar's firm has five major activities. The times (in days) are estimated and provided in the table below:

Activity

Immediate

Predecessor

a m b
A 2 5 8
B 3 6 9
C A 4 7 10
D B 2 5 14
E C 3 3 3

a) The expected completion time for this project is

_____days (enter response as a whole number).

b) The project variance of completion time is

_____days(enter response as a whole number).

c) The probability that this project can be completed in 17 days or less is

______(keep two decimal places).

d) The probability that it will take more than 17 days to complete this project is

_____ (keep two decimal places).

e) The due date that yields a 98% chance of completion is

______(keep two decimal places).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!