Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE
A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below.
| ACTIVITY | IMMEDIATE PREDECESSOR | a | m | b |
| A | 2 | 8 | 14 | |
| B | 3 | 6 | 9 | |
| C | A | 4 | 7 | 16 |
| D | B | 2 | 5 | 8 |
| E | C | 2 | 2 | 2 |
a) Find the expected completion time for this project.
The expected completion time for this project is ________
(enter your response as a whole number).
b) What variance value would be used to find probabilities of finishing by a certain time?
The project variance value of completion time is ________
(enter your response as a whole number).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
