Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE

A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below.

ACTIVITY IMMEDIATE PREDECESSOR a m b
A 2 8 14
B 3 6 9
C A 4 7 16
D B 2 5 8
E C 2 2 2

a) Find the expected completion time for this project.

The expected completion time for this project is ________

(enter your response as a whole number).

b) What variance value would be used to find probabilities of finishing by a certain time?

The project variance value of completion time is ________

(enter your response as a whole number).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!