Question: 2. Activity Preceding activity Normal Time Crash Time Cost to crash A - 5 3 $200 B - 4 3 $300 C A 6 5
2.
| Activity | Preceding activity | Normal Time | Crash Time | Cost to crash |
| A | - | 5 | 3 | $200 |
| B | - | 4 | 3 | $300 |
| C | A | 6 | 5 | $300 |
| D | B | 5 | 4 | $100 |
| E | A, C, D | 7 | 6 | $100 |
| Projects budget per day $500 | ||||
- Draw a AON diagram and determine which activities are on the critical path, its length, and the length of the other path. (2 marks)
- Develop a crashing schedule to show how the activities on the critical and other paths can be crashed. (3 marks)
- After crashing the activities as per the crashing rules what will be the duration of the project? (2 mark)