Question: . For the activities described below: . What is/are the critical path(s) . To shorten the project by 3 weeks, what tasks need to be

. For the activities described below: . What

. For the activities described below: . What is/are the critical path(s) . To shorten the project by 3 weeks, what tasks need to be shortened and what are the associated costs? 2 Activity Preceding task Normal time Crash time Cost A 4 2 $10000 B 3 2 $6000 A 2 1 $4000 D B 5 3 $14000 E B,C 1 1 $9000 F 3 2 $7000 G E,F 4 2 $13000 . DE 4 1 $11000 1 H,G 6 5 $20000 Crash cost $11000 $9000 $6000 $18000 $9000 $8000 $25000 $18000 $29000