Question: 2. Answer the questions based on the activity schedule given below. Activity Immediate Normal Normal Crashing Crashing Predecessor time Cost (FD) Time Cost (FD) A

2. Answer the questions based on the activity schedule given below. Activity Immediate Normal Normal Crashing Crashing Predecessor time Cost (FD) Time Cost (FD) A 3 150 3 150 B 4 200 3 220 C A 4 500 3 575 D AB 5 300 3 400 E C.D 5 400 4 550 F E.D 3 200 2 600 A. Draw the AON diagramme for the above schedule. B. Calculate crash cost per day for each activity C. What is the estimated completion time? D. What is the best option to crash the project to complete in 1 day earlier? E. What are the best options to crash the project to complete in 2 days earlier? F. What are the best options to crash the project to complete in 3 days earlier? G. What are the best options to crash the project to complete in 4 days earlier