Question: 2 . As a contractor you have built a 2 5 6 - unit apartment complex that will rent for $ 1 , 7 5

2. As a contractor you have built a 256-unit apartment complex that will rent for
$ 1,750 a unit per month (assume 30 days/month). You were late in completing the project by 9 days, during which time the owner keeps their construction administration operation running, and are assessed (i.e., asked to pay the owner) $144,000 total based on the project contract. Would this assessment be considered liquidated damages or a penalty? (3pt) Explain the basis for your answer and show your calculations. (5pt)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!