Question: 2 . At the beginning of a project, a software team project manager is given a schedule with everyones vacations on it . She realizes

2. At the beginning of a project, a software team project manager is given a schedule with everyones vacations on it. She realizes that because the software will be delivered to the quality assurance team exactly when they have overlapping vacations, there is a serious risk of quality problems because there wont be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project?
a. Quality constraint
b. Time constraint
c. Resource constraint
d. Risk constraint