Question: 2 . At the beginning of a project, a software team project manager is given a schedule with everyones vacations on it . She realizes
At the beginning of a project, a software team project manager is given a schedule with everyones vacations on it She realizes that because the software will be delivered to the quality assurance team exactly when they have overlapping vacations, there is a serious risk of quality problems because there wont be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project?
a Quality constraint
b Time constraint
c Resource constraint
d Risk constraint