Question: At the beginning of a project, a software team project manager is given a schedule with everyones vacations on it. She realizes that because the

At the beginning of a project, a software team project manager is given a schedule with everyone’s vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems because there won’t be anyone to test the software before it goes into production.

What BEST describes the constraint this places on the project?

A. Quality constraint B. Time constraint C. * Resource constraint D. Risk constraint

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Managers Questions!