Question: 2 Audrey has been charged with breaking down the activities in the WBS into smaller components that can be estimated. Her mentor has suggested that
2 Audrey has been charged with breaking down the activities in the WBS into smaller components that can be estimated. Her mentor has suggested that she contact a more experienced project manager for some advice on some of the activities. What technique does this describe?
Select one:
a. WBS
b. Dependency determination
c. Expert judgment
d. Decomposition
A project manager has received activity duration estimates from his team. Which of the following does he need in order to complete the Develop Schedule process?
Select one:
a. Reserves
b. Schedule change control system
c. Change requests
d. Recommended corrective actions
A project has three critical paths. Which of the following BEST describe how this affects the project?
Select one:
a. It requires more people
b. It makes it more expensive
c. It makes it easier to manage.
d. It increases the project risk
___________ of lessons learned or inputs into iterative processes are designed to improve performance on current and future projects.
Select one:
a. Introspectives
b. Evolutions
c. Corrective action plans
d. Retrospectives
Extreme Programming (XP) defines four basic activities that are performed during the software development process. These include designing, coding, testing and ... ?
Select one:
a. Collaborating
b. Leveling
c. Communicating
d. Listening