Question: 2) Complete the following statement with the correct answer. The five core management processes of the SCOR model are plan, source, make, deliver, and ________.
| 2) Complete the following statement with the correct answer. The five core management processes of the SCOR model are plan, source, make, deliver, and ________. |
| Train |
| Return |
| Test |
| Configure |