Question: 2 . Consider the following project flow diagram. Recall: Flow times for each activity are listed above the activity. The arrows represent which activities need

2. Consider the following project flow diagram.
Recall: Flow times for each activity are listed above the activity. The arrows represent which activities need to be finished before others can start, e.g., A must come before \( C \), but \( A \) and \( B \) can happen simultaneously.
The following table contains information about how much each activity costs. The table also contains information about crash times and crash costs.
(a) What is the critical path in the project?
(b) What is the current duration of the process? (i.e., without any crashing?)
(c) Complete the following table to compute the cost slopes:
(d) If the original activity times are used, then it will cost a total of \(\$ 50\) to complete all activities (i.e., a total of \(\$ 50\) to complete the project). What is the minimum amount of extra money you need to spend in order to reduce the project duration by 2 minutes?
Answer in dollars. For instance, if you reduce the project duration by 2 minutes and it now costs a total of \(\$ 120\) to complete all activities (i.e., a total of \(\$ 120\) to complete the project based on the reduced times), then you will pay an extra \(\$ 120-\$ 50=\$ 70\). Hence, you would write \(\$ 70\).
2 . Consider the following project flow diagram.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!