Question: Complete Exercise 2 items 'a', through 'd' in Chapter 6. Submit PowerPoint slides illustrating your analysis and include typed out answers in your slides. Be

Complete Exercise 2 items 'a', through 'd' in

Complete Exercise 2 items 'a', through 'd' in Chapter 6.

Submit PowerPoint slides illustrating your analysis and include typed out answers in your slides.

Be sure to double-check your work to ensure that you have listed all the paths and durations correctly.

2. Consider Table 6-2. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. (Note that you can easily change this table to create multiple exercises.) TABLE 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration A B 2 3 2. 2 4 3 D 2 5 4 E 3 6 2. F 4 6 3 G 5 7 6 H 6 8 2 I 6 7 5 J 7 8 1 K 8 9 2 a. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path. c. What is the critical path for this project and how long is it? d. What is the shortest possible time needed to complete this project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!