Question: (2) Consider the following project: Immediate Predecessor Optimistic (days) Most Probable (days) Pessimistic (days) Activity A 1 2 3 B A 4 6 8 A

(2) Consider the following project: Immediate

(2) Consider the following project: Immediate Predecessor Optimistic (days) Most Probable (days) Pessimistic (days) Activity A 1 2 3 B A 4 6 8 A 2 4 6 D B, C 1 2 3 E B 2 3 4 F A 1 2 3 G D 1 2 3 H G 1 2 3 I E, H, F 1 1 1 . Draw the Network diagram. Calculate expected time and variance for each activity. Find the critical path. Calculate the total project completion time. Find project variance