Question: 2) Considering the following schedule what would be the minimum cost to shorten the schedule by 6 weeks?? Activity Preceding Activity Cost ($K) Normal Crash

2) Considering the following schedule what would

2) Considering the following schedule what would be the minimum cost to shorten the schedule by 6 weeks?? Activity Preceding Activity Cost ($K) Normal Crash Time (W) Normal 4 3 2 10 A B C A 6 Crash 11 9 6 18 9 A 2 4 B D E 5 1 B, C 3 1 2 2 F 3 8 14 9 7 13 12 20 4. E, F D, E H, G G H . 4 25 18 29 6 5