Question: 2) Considering the following schedule what would be the minimum cost to shorten the schedule by 6 weeks?? Activity Preceding Activity Time (W) Normal Crash

2) Considering the following schedule what would

2) Considering the following schedule what would be the minimum cost to shorten the schedule by 6 weeks?? Activity Preceding Activity Time (W) Normal Crash Cost (SK) Normal 10 6 Crash 11 A 4 2 B 3 2 9 . . C 2 1 4 6 D B 5 3 14 18 E 1 1 9 9 F 3 2 G B, C E, F D, E HG 4 2. 7 13 12 8 25 18 29 4 1 H 1 6 5 20