Question: 2 days 4 days Activity Expected Pessimistic 1 day durations durations Act. 2 Act. 1 Act. 5 P IN 2 4 6 3 1 2

 2 days 4 days Activity Expected Pessimistic 1 day durations durations

2 days 4 days Activity Expected Pessimistic 1 day durations durations Act. 2 Act. 1 Act. 5 P IN 2 4 6 3 1 2 1 day 2 days 4 2 4 Act. 3 Act. 4 5 2 If the activities cost $100 per day how much contingency should be set aside if instead of planned duration shown on the network the pessimistic durations are realized for the project shown above : 800 900 400 not enough information