Question: 2: Determine the project duration for the following table using Bar chart. Activity Preceded by Duration (days) A 1.5 B A 1.5 A 2.5 D

2: Determine the project duration for the

2: Determine the project duration for the following table using Bar chart. Activity Preceded by Duration (days) A 1.5 B A 1.5 A 2.5 D B 1 E CD 1.5 F D 1 G F 3.5 H G 1 I G 0.5 J G 1