Question: (2) Draw Activity-on-Arrow network diagram for the project given below: (1) A is the first operation on the project. (2) B and C can be

(2) Draw Activity-on-Arrow network diagram for

(2) Draw Activity-on-Arrow network diagram for the project given below: (1) A is the first operation on the project. (2) B and C can be done concurrently and both must follow A. (3) B must precede D. (4) E cannot begin until both B and C are completed. (5) F is dependent on the completion of both D and E. (6) F is the last operation on the project