Question: 2. For project y that is given in table 2, we have the activities, immediate precedence, optimistic time, most likely time and pessimistic time. For

2. For project y that is given in table 2, we have the activities, immediate precedence,

optimistic time, most likely time and pessimistic time. For the given condition:

a) Develop the network diagram

b) Find the critical path

c) Find the expected time

d) Find the probability of completing the project within 35 and 45 days

Table 2 different activities for a project and optimistic time, most likely time and pessimistic

time of the activity

Activities

IP

To

Tm

Tp

A

5

7

12

B

6

8

11

C

8

10

14

D

A

7

9

12

E

B

8

10

12

F

C

7

8

13

G

D

6

8

11

H

D

4

7

12

I

F

4

6

9

J

H,E

8

13

19

K

G

11

14

17

L

I

13

16

22

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!