Question: 2. For project y that is given in table 2, we have the activities, immediate precedence, optimistic time, most likely time and pessimistic time. For
2. For project y that is given in table 2, we have the activities, immediate precedence,
optimistic time, most likely time and pessimistic time. For the given condition:
a) Develop the network diagram
b) Find the critical path
c) Find the expected time
d) Find the probability of completing the project within 35 and 45 days
Table 2 different activities for a project and optimistic time, most likely time and pessimistic
time of the activity
| Activities | IP | To | Tm | Tp |
| A |
| 5 | 7 | 12 |
| B |
| 6 | 8 | 11 |
| C |
| 8 | 10 | 14 |
| D | A | 7 | 9 | 12 |
| E | B | 8 | 10 | 12 |
| F | C | 7 | 8 | 13 |
| G | D | 6 | 8 | 11 |
| H | D | 4 | 7 | 12 |
| I | F | 4 | 6 | 9 |
| J | H,E | 8 | 13 | 19 |
| K | G | 11 | 14 | 17 |
| L | I | 13 | 16 | 22 |